Juq-867 Eng Sub Jun 2026

| Risk ID | Description | Impact | Probability | Mitigation Strategy | Owner | Status | |---------|-------------|--------|-------------|---------------------|-------|--------| | | Lead‑time extension for aluminum alloy | Schedule (+2 wks) | Medium | Qualify secondary supplier (Supplier‑B) – already under NDA. | Procurement Lead | Mitigation in place | | R‑02 | MCU‑XYZ obsolescence | Design redesign & re‑validation | High | Switch to MCU‑ABC; update schematics, run regression tests. | Electrical Eng. Lead | Action started | | R‑03 | Software latency > spec | Functional performance shortfall | High | Refactor middleware to event‑driven architecture; benchmark by [Date] . | Software Lead | In progress | | R‑04 | NCR‑001 (mounting bracket tolerance) | Potential assembly issues | Low | Issue corrective drawing; re‑issue to vendor. | Mechanical Lead | Resolved | | R‑05 | Test facility availability (COVID‑related) | Delayed SIT | Low | Reserve alternative test chamber at Partner Lab. | Test Manager | Contingency ready |